X and Y together need to complete a piece of work in 15 days. They both start working together, but after 6 days Y falls ill, so X takes 30 more days to complete the work alone. How long will Y take to complete the work alone?
(3 marks)

Open in App
Solution

(X+Y)'s 1-day work = 115
(X+Y)'s 6-day work = 615
Remaining work = 1 - 615 = 915 = 35 (1 mark)
X takes 30 days to complete remaining work.
X's 1-day work = 3530 = 150
So, X takes 50 days to complete full work alone.
(1 mark)
Y's 1-day work = 115 - 150 = 7150
Y takes 1507 or 21.4 or 21 days (approx.)
(1 mark)