X is half as good a workman as Y and together they finish a piece of work in 28 days. The number of days taken by X alone to finish the work is?
84
Let the time taken by X to complete the work be ‘2x’ days.
The time taken by Y to complete the work will be ‘x’ days.
12x+1x=28
x=42days (Time taken by ‘Y’)
∴Time taken by X=2x=84 days