How to Calculate Early Start and Early Finish in CPM?
The formula used for calculating the Early start and Early finish in CPM is as follows:
Early Start of the activity = Early Finish of predecessor activity + 1
Early Finish of the activity = Activity duration + Early Start of activity – 1