CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

10 Men begin to work together on a job, but after some days, 4 if them left the job. As a result the job which could have been completed in 40 days is completed in 50 days. How many days after the commencement of the work did the 4 men level?

A
25
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
30
No worries! Weā€˜ve got your back. Try BYJUā€˜S free classes today!
C
10
No worries! Weā€˜ve got your back. Try BYJUā€˜S free classes today!
D
15
No worries! Weā€˜ve got your back. Try BYJUā€˜S free classes today!
Open in App
Solution

The correct option is A 25
10 Men begin work
It could been done in 40 days.
Let 4 men left after x days.
Left days are 40x if they do not left and 50x if they left.
(40x)10=(50x)6
40010x=3006x
1000=4x
x=25 days.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon