CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job . if 6 men. leave after working for 6 days?

A
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
24 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is D 12 days
12 men can complete in 12 days 1 work 1 man can complete in 1 day 112×12 part of the work
men can complete in 6 days
6×612×12 part of the work = 14th of the work Number of remaining men = 6
Remaining work = 34 12 men can complete 1 work in 12 days
6 men can complete 34 work in 12×12×36×4=18 days
Number of extra days = 18 - 6 = 12 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon