10 men can complete a piece of work in 10 days. In how many days will 5 men complete the same work.

A
20 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
15 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 20 days
The number of men (M) required to complete a work is directly proportional to the amount of work (W).

M W...(1)

The number of men (M) required to complete a work is inversely proportional to the number of days required to do the work (D).

M1D...(2)

Combining (1) and (2), we get,

MWD

Let k be the constant of variation.
So, M=kWD

MDW=K(constant)

Let the number of days required to complete the same work by 5 men be x days.

Hence, (10)(10)W =(5)(x)W

So, x = 20 days.



flag
Suggest Corrections
thumbs-up
6
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon