CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?

A
2012days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2035days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
21 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
2047days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is C 2047days
8 men working for 9 hours a day can complete a piece of work in 20 days
8 men working for 1 hour a day can complete the work in (20 x 9) days (Less hours, More days)
1 man working for 1 hour a day can complete the work in (20 x 9 x 8) days (Less men, more days)

1 man working for 10 hours a day can complete the work in (20×9×810) days

7 men working for 10 hours a day can complete the work in (20×9×87×10) days = 1447 days = 2047 days

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon