Working 7 hours daily 24 men can complete a piece of work in 27 days. In how many days would 14 men complete the same piece of work working 9 hours daily?
A
36 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
30 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
32 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A 36 days We have M1=24D1=27,W1=1,t1=7,