CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

6 men working 9 hours a day can do a piece of work in 4 weeks. How many men are required working 8 hours a day for 3 weeks to complete the same work?
  1. 9

Open in App
Solution

The correct option is A 9
Here, the number of men is inversely proportional to the number of hours and inversely proportional to the number of days.
Number of men Number of hours Number of days
6 9 4×7=28
x 8 3×7=21
6:x 9:8 28:21 = 4:3

Number of men1Number of hours
6 : x = 8 : 9 ...(i)

Number of men1Number of days
6 : x = 3 : 4 ...(ii)

From (i) and (ii)
6 : x
=compound ratio of 8 : 9 and 3 : 4
6 : x=(8 : 9) × (3 : 4)
6 : x=(8 × 3) : (9 × 4)
6 : x=(24 : 36) = (2 : 3)

Product of means = Product of extremes
x × 2 = 6 × 3
x = 9

Hence, 9 men are required to finish that work in 3 weeks working 8 hours a day.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Concepts
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon