wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

10 men working 6 hours a day, can complete a work in 18 days. How many hours a day must 15 men work, to complete the same work in 12 days?

A
4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
6
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
7
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 6
To complete the work in 18 days 10 men work 6 hours day
To complete the work in 18 days 1 man work (10 x 6) hours a day
To complete the work in day 1 man will work (6 x 10 x 18) hours in a day (less days, less men, more hours)
To complete the work in 1 day 15 men will work (6×10×18)15 hours a day
To complete the work in 12 days 15 men will work 6×10×1812×15 hours a day
(more days, more men, less hours) = 6 hours a day

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon