12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days?
15
1 man’s 1 day’s work =148 ,
1 woman’s 1 day’s work = 160
6 men’s 2 day’s work = (648×2)=14
∴ Remaining work = (1−14)=34
Now,160 work is done in 1 day by 1 woman.
So,34 work will be done in 3 days by =(60×34×13)=15 women