$$24$$ men can complete a work in $$16$$ days, $$32$$ women can complete the same work in $$24$$ days. $$16$$ men and $$16$$ women started working and worked for $$12$$ days. How many more men are to be added to complete the remaining work in $$2$$ days?


A
16
loader
B
24
loader
C
36
loader
D
48
loader

Solution

The correct option is C $$24$$
24 men can complete the work in 16 days
1 man can complete the work in $$=16\times 24=384  Days$$
 32 women cam complete the work in 24 days
1 woman can complete the work in a$$=32\times 24=768  days$$
Ratio between man and woman$$=384:768=1:2$$
then 1 man =2 women
The work is done br 16 men and 16 women in 12 days
16 women=8 men
thus the number of men complete the work in 12 days=$$16+8=24  men$$
Since 24 men takes 16 days to complete the work
So after 12 days,4 days work will be left for 24 Men
Thus the work left can be completed in 2 days by$$=24\times \dfrac{4}{2}=48  Days$$
Additional men required to complete the work in 2 days$$=48-24=24  men$$