CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
5
You visited us 5 times! Enjoying our articles? Unlock Full Access!
Question

12 painters can paint a wall of 180 m long in 3 days. How many painters are required to paint a 200 m long wall in 5 days?

A
18
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
24
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
20
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
8
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 8

Since, number of painters α length of the wall and,

number of painters α 1number of days

Therefore, 12 : x = compound ratio of 9 : 10 and 5 : 3

So, 12 : x = (9 : 10) × (5 : 3)
Or, 12 : x = 9 × 5 : 10 × 3
Or, 12 : x = 45 : 30
Or, 12 : x = 3 : 2
x=12×23=8
Thus, 8 painters are required to paint a 200 m long wall in 5 days.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Ratio and Proportion
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon