16 men can do a piece of work in 14 days. How long will it take for 7 men to do the same work?
34 days
30 days
28 days
32 days
More men, less days; less men, more days MenDays1614114×16714×167=32 ∴ 7 men will take 32 days to do the same work.
If 12 men and 16 boys can do a piece of work in 5 days and 13 men and 24 boys can do it in 4 days, how long will 7 men and 10 boys take to do it?