wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

16 men can do a piece of work in 16 days. 4 days after they started the work 8 more men joined them. How many days will they now take to complete the remaining work?

A
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
12 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Join BYJU'S Learning Program
CrossIcon