16 men can do a piece of work in 16 days. 4 days after they started the work 8 more men joined them. How many days will they now take to complete the remaining work?
A
10days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
6days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
12days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is D8days 16 men can do work in 16 days 16×16=16×4+24×x x=16[16−4]24=8days