The correct option is B 12
Given that 16 workers take 48 hours to build the wall. If the time is reduced to 32 hours, then let the number of workers required be y.
16×48= y×32
y=24
Now, if 4 workers left, the remaining number of workers at the site is 16−4=12
Thus, additional number of workers required will be
24−12=12