18 men can complete a piece of work in 6 hours, while 30 women can complete the same work in 8 hours. 9 men start working on the job and after working for 3 hours, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 6 hours?
30
1 man`s 1 hour's work = 118×6=1108
1 woman`s 1 hour's work = 130×8=1240
9 men's 3 hour's work = 9108×3=14
Remaining work = 1−14=34
Now, 1240 work is done in 1 hour by 1 woman
So, 34 work will be done in 6 hours by 240×34×16 = 30 women