3 men and 4 women do a work in 10 days as 2 men and 6 women do.4 men and 8 women starts the same work and after 2 days only women remains in the work for completing it. How many days are required to complete the work?
A
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
7.5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
8.5 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D8.5 days Given, 3 men +4 women =2 men + 6 women.
Therefore, 1 man = 2 women Now, 4 men +8 women = 16 women.
According to question, 3 men +4 women =10 women do the work in 10 days So 1 day work of 1 woman =1100 part In 2 days work completed =2×16×1)100 =32100 part Remaining work =68100 part and Remaining women for work =8 So number of days required =68/100)(8/100)=688=172 =8.5