The correct option is A 12
Let the required number of working hours per day be x.
More pumps, Less working hours per day (Indirect Proportion)
Less days, More working hours per day (Indirect Proportion)
Pumps4:3Days1:2}::8:x
∴4×1×x=3×2×8
⇒x=(3×2×8)(4)
⇒x=12