CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

36 workmen are employed to finish a certain work in 48 days but it is found that in 24 days , only 25 work is done. How many more men must be taken to finish the work in time?

A
16
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
20
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
18
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 18
25=(2×100)5=40% work completed in 24 days
so, 60% more is required to complete in 24 days
If 36 worker works for rest 48 days then work will be 80%completed.
To complete 20 more work within the time they need 18 workers more.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon