4 men and 6 women complete a piece of work in 24 days then how many men to join three women to complete the work in 16 days? Please solve it mathematically and show.

Open in App
Solution

If 4 men can do the work in 24 days, one man in one day does 1/4 x 1/24 or 1/96 of the work.

If 6 women can do the work in 24 days, one woman in one day does 1/6 x 1/24 or 1/144 of the work

3 women in 16 days will do 3x16/144 or 48/144 or 1/3 of the work.

2/3 remains to be done by the men. That’s 64/96. One man will do 16/96 of the work in 16 days. So 64/16 or 4 men are needed.

Hope it helps