CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

6 men can complete theelectric fitting in a building in 7 days. How many days will it take if 21 men do the job?

Open in App
Solution

6 men can complete the work in =7 days

1 man will complete the same work in = 7×6 days

(Less men, more days)

21 men will finish the work in =7×621 days

(More men, less days)

=2 days


flag
Suggest Corrections
thumbs-up
86
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon