Question

68. A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:


A

(a) 9 1/5 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

(b) 9 2/5 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

(c) 9 3/5 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
(d) 10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C

(c) 9 3/5 days


Ans68.(c)
Explanation:
(A+B+C)’s 1 day’s work = 1/4
A’s 1 day’s work 1/16
B’s 1 day’s work 1/12
C’s 1 day’s work = 1/4*(1/16+1/12)=(1/4-7/48)=5/48
So, C alone alone can do the work in 48/5=9(3/5) days

flag
Suggest Corrections
thumbs-up
20
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon