8 men can complete a work in 6 weeks. After they have worked for 4 weeks, 4 more men join them. How many weeks will they take to complete the remaining work?


A

2 weeks

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

3 weeks

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

4 weeks

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

5 weeks

No worries! We‘ve got your back. Try BYJU‘S free classes today!
E

4/3 weeks

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses