Question

9 masons working 25 days a month for 8 months can build a platform of width 60 meters, length 10 meters and height 28 meters. How many months will 12 masons working 30 days a month take if they have to build a platform of width 200 meters, length 14 meters and height 36 meters?


A

30

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B

24

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

20

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

18

No worries! We‘ve got your back. Try BYJU‘S free classes today!
E

25

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A

30


9 workers work for 25 days a month for 8 days = 60×10×28

12 workers work for 30 days a month for ‘n’ days =200×14×36

Taking the ratio, n = 30 months


flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Percentages and Why Percentages
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon