9 masons working 25 days a month for 8 months can build a platform of width 60 meters, length 10 meters and height 28 meters. How many months will 12 masons working 30 days a month take if they have to build a platform of width 200 meters, length 14 meters and height 36 meters?
30
9 workers work for 25 days a month for 8 days = 60×10×28
12 workers work for 30 days a month for ‘n’ days =200×14×36
Taking the ratio, n = 30 months