A and B can complete a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in?
10 days
Let A take a days, B take b days and C takes c days to complete the work.
2(1a+1b+1c)=112+115+120
Total work would be done in 10 days if they work together.