wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

A
30 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
40 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
60 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
70 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 60 days
LetthetotalworkbeW.
LetthespeedofAindoingentireworkbexwork/day
LetthespeedofBindoingentireworkbeywork/day
Wx+y=30
W=30x+30y............(1)
WorkdonebyAin16days=16x
RemainingworkdonebyBin44days=44y
16x+44y=W.........(2)
From(1)and(2),W=60y
Hence,ifBworksalonethentheworkwillbecompletedinWydays=60yydays=60days.

flag
Suggest Corrections
thumbs-up
5
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon