A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in how many days?
24/7 days
(A+B+C)’s 1 day’s work = (124 + 16 + 112) = 724
So, A, B and C together will complete the job in 247 days.