A. B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together. but C left after 2 days. In how many days will the remaining work he completed by A and B?
A's one day's work =115
B's one day's work =112
C's one day's work =120
A,B and C's one day's work
=115+112+120
=4+5+360 (LCM of 15,12,20=60)
=1260=15
A,B and C's 2 days work =15×2=25
Remaining work =1−25
=5−25=35 A and B's one days work =115+112
=4+560=960=320
∴ A and B will do the remaining work 35in=203×35=4 days