Question

A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before completion. The number of days for which C worked is

A
4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
8
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
24
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 24
A does the work in 36 days.
In 1 day A does 136 work.
B does the work in 54 days.
In 1 day B does 154 work.
C does the work in 72 days.
In 1 day C does 172 work.
Let the work is finished in x days.
So A works for x-8 days.
A does x836 work
B works for x-12 days.
B does x1254 work.
C works for x days.
C does x72 work.
The sum of their works = the whole work = 1 work.
x836+x1254+x72=16x48+4x48+3x216=113x96216=113x=312x=24
So the work is finished in 24 days.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon