The correct option is
C 2212days
Let the amount of work be
x.
Now A does the work in 25 days.
∴ In 1 day A does x25 work,
B does the work in 20 days.
∴ In 1 day B does x20 work,
C does the work in 24 days.
∴ In 1 day C does x24 work.
A works for (2+3) days =5 days.
∴ In 5 days A does 5×x25 work = x5 work,
B works for 2 days.
∴ In 5 days B does 2×x20 work=x10 and
C works for (2+835+3)days=685days.
∴ In 685 days C does 685×x24 work=17x15 work.
∴ The total work done by A,B and C, so far = x5+x10+17x13 work = 13x15 work.
∴ The work left = x−13x15 work
This work is done by D in 3 days.
∴ D will finish the whole i.e x work in 3×152days =2212 days.
Ans- Option D.