Question

A. B and C together can do a piece of work in 40 days. After working with B and C for 16 days, A leaves and then B and C complete the remaining work in 40 days more. A alone could do the work in

A
80 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
90 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
100 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
120 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 100 days
Let the total work be 80 units. [LCM of 40 and 16]
(A + B + C) do = 8040 = 2 units/day
(A + B + C) work for 16 days, complete 16× 2 = 32 units of work
Work left is 8032=48 units.
B and C do = 4840 =1210 = 1.2 units/day
A does = 21.2 units = 0.8 unit/day
A will complete the work in = 800.8 = 100 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Adaptive Q28
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon