A,B,C,D and E are the 5 activities along the unique critical path of a AOA network of activities. Their characteristics are as under:
Activity A B C D E
Expected~duration,~days 7 6 11 14 5
Standard deviation, days 2 2 3 4 1

What is the possible range of project duration (in days)?

A
24.6 to 61.4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
31.2 to 54.8
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
28.1 to 57.9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
25.55 to 60.5
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 25.55 to 60.5
Project duration, te=7+6+11+14+5
=43 days
Variance =22+22+32+42+12=34
Standard deviation σ=34=5.8
Range of project duration = (Minimum time, Maximum time)
Minimum time =(T3σ=25.6) days
Maximum time =T+3σ=60.4 days

flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Standard Deviation
STATISTICS
Watch in App
Join BYJU'S Learning Program
CrossIcon