A borrow pit soil has a dry density of 17kN/m3. How many cubic meters of this soil will be required to construct an embankment of 100m3 volume with a dry density of 16kN/m3 .
A
94m3
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
106 m3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
100 m3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
90 m3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A 94m3 Given
Phase diagrams
Volume of borrow pit soil will be required to construct an Embankment of 100m3 = 94.12m3