Question

A brazing operation was studied. The operator under the study has performance rating of 110%. The operator took 1 hour to braze 18 joints. If a total of 10% allowances are allowed for the operation. The expected standard production rate of the joints (in units per 5 hour shift) is:

A
45
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
75
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
90
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
60
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 75
Elemental time for 1 brazing =118hr=6018min.

Normal time = Elemental time × rating factor

=6018×1.1

Standard time = Normal time + allowances

=6018×1.1+10100×6018×1.1=4.033 min.

Standard Production rate =5×604.03375

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
The Cost Curve
ECONOMICS
Watch in App
Join BYJU'S Learning Program
CrossIcon