A can complete a piece of work in 18 days, B in 20 days and C in 30 days. If B and C together start the work and are forced to leave after 2 days, then number of days taken by A alone to complete the remaining work is
A
10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
15
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
16
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C15 Two day's work of (B+C)=2×(120+130)=16
Remaining work =1−16=56
One day's work of A=118
Hence, number of days taken to complete the work =5/61/18=15