CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A can complete a piece of work in 18 days. B is 20% more efficient than A. The number of days B takes to complete the same piece of work is ?

A
15
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 15
Efficiency is inversely proportional to the number of days needed to do the work.

More efficiency means less number of days needed to complete the work.

If efficiency of A is 100, then efficiency of B is 20% more that is 120.

The ratios of efficiency of A and B is
AB (efficiency) =100120=56

A completes the work in 18 days and let B complete the work in x days.

The ratio of number of days needed to complete the work by A and B is,
AB (days) =18x

Now efficiency is inversely proportional to number of days so AB is
56 =x18

6×x=5×18

x=15 days

B would complete the work in 15 days.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon