A can do a piece of a work in 7 days, A and B can do the work together in 6 days. If B alone does the work how many days does he require?
42
Let the time taken by B be ‘x’
A can do the work in 7 days.
Hence the work done by A in one day = 17
A and B can together finish the work in 6 days
Hence the work done by A and B in one day = 16
∴ work done by B in one day = Work done by A and B in one day - work done by A in one day
= 16 - 17
= 7−642
= 142
Since Work done by B in one day is 142 , B alone can complete the work in 42 days