A can do a piece of work in 14 days and B in 21 days. They begin together, but 3 days before the completion of the work, A leaves off. In how many days is the work complete?
A
10days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
1015days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
15days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
7days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B1015days (A+B)′s1 day work =114+121=3+242=542 At the end, B works for 3 days so work done by B in 3days=3×121=17. Remaining work 1−17=67 which is to be done by A and B. 542 of work (A+B) can do in 1 days ∴67 of work (A+B) can do in 15/42×67=715days ∴ Time to complete the work =3+715=1015days.