A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is:
The correct option is C. 1015
Amount of work done by A in 14 days =114 units of work
Amount of work done by B in 21 days =121 units of work
(A+B)’s 1 day’s work =(114+121)=542 units of work
Now, B’s 3 days’ work =(121×3)=17
Remaining work =(1−17)=67
Now, 542 work is done by A and B in 1 day
∴ 67 work is done by A and B in (425×67)=365days
Hence, total time taken to complete the work =(3+365) days = 1015 days