wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A can do a piece of work in 14 days while B can do it in 21 days. They began together and worked at it for 6 days. Then, A fell ill and B had to complete the remaining work alone. In how many days was the work completed?

Open in App
Solution

Time taken by A to complete the work =14 days
i.e., Work done by A in one day =114
Time taken by B to complete the work =21 days
i.e., Work done by B in one day =121

Work done jointly by A and B in one day =114+121
=3+242=542
Work done by A and B in 6 days =542×6=57
Work left =157=757=27

With B working alone, time required to complete the work

=27÷121 [Since, Work done by B in one day is 121]

=27×21

=2×3

=6 days

Hence, B complete the remaining work in 6 days, previous work done By A and B in 6 days.

So, the total time taken to complete the work =6+6=12 days


flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Year, Leap Year and Dates
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon