wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A can do a piece of work in 24 days while B can do it in 30 days. In how many days can they complete it, if they work together ?

Open in App
Solution

Let total works =x
A takes 24 days to complete x
In one day a complete work =x24
B completes x works in 30 days
In 1 day B completes work =x30
If A and B work together,
work done in one day =x24+x30
=5x+4x120=9x120=3x40
Let they take n days to complete entire work.
Total work =n×3x40=x
n=403 days

flag
Suggest Corrections
thumbs-up
3
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Linear Equation in 2 Variables
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon