Question

A can do a piece of work in 30 days, B can do in 45 days and C can do same work alone in 60 days. If on the first day A worked alone and on the second day A and B worked together and on the third day A and C worked together. If they repeat the cycle as follows then in how many days total work can be completed?

A
21 Days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
21 7/8 Days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
21 5/6 Days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
21 4/9 Days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 21 5/6 Days

First day = 1/30; Second day = 1/30+1/45; Third day = 1/30+1/60
3 days work = 3/30+1/45+1/60 = 25/180
3*7 = 21 days work = 175/180
Now 1/36 work is left which can be completed by A alone
1/36*30 = 5/6
21+5/6 = 21 5/6 Days


flag
Suggest Corrections
thumbs-up
7
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon