Question
A can do a piece of work in 4 days and B can do the same work in 5 days. Find, how much work can be done by them working together in:
2 days.
Open in App
Solution
It is given that
A can do a piece of work in 4 days B can do the same work in 5 days
A's one day's work = 1/4
B's one day's work = 1/5
A and B both one-day work
=
1
4
+
1
5
=
5
+
4
20
=
9
20
A and B two day's work =
9
20
×
2
=
9
10
Suggest Corrections
0
Similar questions
Q.
A can do a piece of work in 4 days and B can do the same work in 5 days. Find, how much work can be done by them working together in:
(i) one day
(ii) What part of work will be left, after they have worked together for 2 days?
Q.
Ram can do a piece of work in 6 days and Shyam can finish the same work in 12 days. How much work will be finished if both work together for 2 days?
Q.
Ram can do a piece of work in
12
days. Amol can do the same work in
6
days. If they work together, how many days will they finish the work ?
Q.
A
can do
1
2
of a piece of work in 5 days,
B
can do
3
5
of the same work in 9 days and
C
can do
2
3
of that work in 8 days. In how many days can the three of them together do the work ?
Q.
Rakesh can do a piece of work in 20 days. How much work can he do in 4 days?
View More
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Related Videos
Time and Work
MATHEMATICS
Watch in App
Explore more
Time and Work
Standard VII Mathematics
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Solve
Textbooks
Question Papers
Install app