Question

A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days can the two of them complete the work together ?

A
20 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
25 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
30 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
35 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 30 days
A's 1 days' work =180
A's 10 days' work =1080=18
Remaining work =118=78
78 of the work is completed by B in 42 days
The whole work is completed by B in 42×87 days = 48 days
B's 1 days' work =148
(A + B)'s 1 days' work =180+148=3+5240=8240=130

A and B can complete the whole work together in 30 days

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Adaptive Q2
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon