Question

A can do a piece of work in 9 days and B in 18 days. They began the work together but 3 days before the completion of work A leaves. The time taken to complete the work is:

A
7 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
11 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is D 8 days
Work done by A in 1 day =19

Work done by B in 1 day =118

Work done by B in last 3 days =118×3=16
Remaining work=116=56

Work done by A and B in 1 day =19+118=318=16
Hence no. of days in which A and B worked together is =5616=5 days
Then total time to complete the work =3+5=8 days.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Let's Add Fractions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon