A can do 14 of a work in 5 days and B can do 13 of the same work in 10 days. Find the number of days in which both working together will complete the work.
A can do 14 of work in = 5 days
∴ A can do 1 work in =5×4 days
= 20 days
B can do 13 of work in = 10 days
∴ B can do 1 work in =10×3 days
= 30 days
∴ A's 1 day work =120
B's 1 day work =130
(A+B)'s 1 day work =120+130
=3+260
=560
=112
∴ A and B working together will complete the work in = 12 days.