A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
A
5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
112 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
6 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C6 days A can finish the work in 18 days Work rate of A =10018=5.55% pr day B can complete the work in 15 days Work rate of B =10015=6.66% per day Work done by B in 10 days =6.66%×10=66.6% Work left =100−66.6=33.33% So, A will complete this work in,' 33.335.55=6 days