A certain number of men can finish a piece of work in 100 days. If, there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally ?
A
75
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
82
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
100
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
110
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D 110 Let the original number of men=x.
So, x men finish the work in100days.
After 10 men leave,
x−10 men finish the work in (100+10)=110days.
Now the number of men is inversely proprtional to the number of days