Question

A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men?

A
1
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
54
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
74
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
32
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 1
After 25 days, 35 men complete the work in 12 days.
Thus, 35 men can finish the remaining work in 12 days.
30 men can do it in (12×35)30=14days,
which is 1 day behind.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon