A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men?
A
1
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
54
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
74
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
32
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A1 After 25 days, 35 men complete the work in 12 days.
Thus, 35 men can finish the remaining work in 12 days. ∴30 men can do it in (12×35)30=14days,
which is 1 day behind.